| Project Name & Location | Duration | Employer/Donor | Total Project Cost in US$ | Service Fee (US$) |
| Construction Management and Construction Supervision of Kulekhani III Hydroelectric Project(14 MW) | Jan 2008 - Oct 2012 | Nepal Electricity Authority (NEA) | 1.94 million | |
| Construction Management and Construction Supervision of Chameliya Hydroelectric Project (30 MW) | July 2007 - May 2011 (Estimated) | Nepal Electricity Authority (NEA) | 1.67 million | |
| Detailed Survey of Upper Trishuli 3A - Matatirtha 220 kV Transmission Line (45.3 km Horizontal Distrance) | July 2007 - March 2007 |
Nepal Electricity Authority (NEA) | 21,410 |
|
| Feasibility Study and EIA/SIA Study of Lower Kokcha Hydropower Project (about 100 MW) | March, 2006- July, 2006 |
Ministry of Energy and Water (MEW) Government of Afghanistan Fichtner GmbH & Co. KG, Germany |
0.16 million |
|
| Feasibility Study & EIA of Lower Hongu Khola HEP (23 MW) | Sept 2005 - Jan 2008 | Department of Electricity |
|
0.098 million |
| Feasibility Study of Mailun Khola Hydropower Project (5 MW), Rasuwa District | Apr., 2000 - Nov., 2000 | Molnia Power Pvt. Ltd. | 10.71 million |
0.024 |
| IInd Phase Feasibility Study of Sharada - Babai Hydropower Project (92 MW) | Jan., 2000 - Dec., 2000 | Department of Electricity Development, GoN |
|
51,000 |
| Detailed Feasibility Study on Commercial Utilization of Natural Gas Resources of Kathmandu Valley | Mar 1996 - September 1996 | DMG/GoN | - |
0.032 |
| Sunsari-Morang New Headworks Project - 2.6 MW Hydropower System- Design & Supervision | Apr., 1991 - May, 1996 | DOI/The World Bank | - |
0.18 |
| Project for Special Assistance for Oil Supply- Design of POL Storage Tanks | August 19, 1992- 1993 | Nepal Oil Corporation Ltd. (NOC)/As DB |
|
0.105 millions |