| Project Name & Location | Duration | Employer/Donor | Total Project Cost in US$ | Service Fee (US$) |
| Updating of the Development Study on Improvement of Water Supply Facilities in Urban Centres and Kathmandu Valley | January 2009- March 2009 |
JICA, Nepal | 0.13 million | |
| Project Management Consultant, Melamchi Water Supply Project, the largest and most complex Project ever implemented in Nepal with the construction of 27 km of tunnel | Dec., 2001 - Oct, 2009 | MWIDB/ADB [ADB LOAN 1820 - NEP (SF)] |
464 million | 2.80 million |
| Project Implementation Consultant, Small Town Water Supply and Sanitation Sector Project (in about 35 towns of Nepal) | Aug, 2001 - Nov, 2008 | DWSS/ADB [LOI/L 1755 - NEPAL (SF)] |
53.2 million | 1.17 million |
| Project Management Consultant Fourth Rural Water Supply and Sanitation Sector Project/Project Management, Western, Mid-western and Far Western Development Region | Sept., 1997 - Jun, 2002 | DWSS/ADB [ADB LOAN 1464-NEP (SF)] |
23.5 million | 0.40 million |
| Project Management Consultant, Third Rural Water Supply and Sanitation Project | Jul, 1997 - Dec., 2002 | DWSS/ADB [ADB Loan 1165 - NEP (SF)] |
25 million | 0.41 million |
| Foothill Water Supply Development Project | Jan 1999- July 1999 |
Nepal Water Supply Corporation | 0.021 million | |
| Design and Supervision of Urban Water Supply and Sanitation Rehabilitation Project in Kathmandu Valley Towns | Aug., 1991 - Jun., 1999 | NWSC/The World Bank (IDA CREDIT 2239 NEP) |
23 million | 0.93 million |
| Consumer Survey For Nepal Water Supply Corporation, Kathmandu Valley Towns, Nepal (128,000 households) | May, 1996 - March, 1998 | NWSC/The WORLD BANK (IDA Credit 2239 - NEP) | - | 0.6 million |
| Community Water Supply and Sanitation Project | December 1994 - October 1995 | Commission of the European Communities | 0.061 million | |
| Kodku Khola Water Supply Project, Kathmandu Valley | May, 1993 - Aug, 1995 | NWSC/PWA of Thailand | 28 million | 0.20 million |